We have a proven track record and building high-quality solutions for customers all over Saudi Arabia. Browse through our previous projects to find one that is similar to yours.
2020
2019
2018
2017
2016
2015
2014
2013
2012
2011
2010
2009
2008
2007
2006
2005
2004
2003
2002
2001
2000
1999
1998
1997
1996
1995
1994
1993
1992
1991
1990
1989
1988
1987
1986
1985
1984
1983
1982
1981
1980
1979
1978
1977
1976
1975
1974
1973
1972
1971
1970
Construction of 40,000 m3/d Dam Water Pre-Treatment Plant comprised of many process concrete water structures/tanks/ ( 5000 to 40,000  m3 ), many buildings, roads, 4000KW Power Plant, Product Water Pumping Station(40,000 m3/hr at 20 bar), 6 km long 800mm diameter ductile iron Dam Water Gravity Pipeline and 1 km long 500mm diameter ductile iron product water pressure pipeline to connect it to existing 500mm diameter water transmission pipeline.
Two Pumping Station Complexes, each complete with two to three underground concrete Reservoirs (5000 to 11,800 m3), Pumping Room ( 6X209 m3/hr), Power Plant, Surge Protection, Chlorination System, many Buildings, Workshop, Guard House, Boundary Wall, Tanker Filling Point and  40 km long underground ductile iron pipeline (400 to 600 mm diameter) for transfer of water from Al-Arbek dam to Al-Makhwa.
Two Pumping Station Complexes, each complete with two to three underground concrete Reservoirs (5000 to 11,800 m3), Pumping Room ( 6X209 m3/hr), Power Plant, Surge Protection, Chlorination System, many Buildings, Workshop, Guard House, Boundary Wall, Tanker Filling Point and  40 km long underground ductile iron pipeline (400 to 600 mm diameter) for transfer of water from Al-Arbek dam to Al-Makhwa.
Construction of 75,000 m3/d RO Water Treatment Plant ( Designed capacity extendable to 100,000 m3/d)  comprised of many concrete water tanks( 5000 to 100,000  m3 ), many buildings, roads, Power Plant and Product Water Pumping Station( Designed Capacity 100,000 m3/d at 30 bar) with 2 km long 1000 mm diameter ductile iron Pipeline connected to existing 70km long 1000mm diameter ductile iron water transmission pipeline going to Bish.
Construction of 75,000 m3/d RO Water Treatment Plant ( Designed capacity extendable to 100,000 m3/d)  comprised of many concrete water tanks( 5000 to 100,000  m3 ), many buildings, roads, Power Plant and Product Water Pumping Station( Designed Capacity 100,000 m3/d at 30 bar) with 2 km long 1000 mm diameter ductile iron Pipeline connected to existing 70km long 1000mm diameter ductile iron water transmission pipeline going to Bish.
Construction of 75,000 m3/d RO Water Treatment Plant ( Designed capacity extendable to 100,000 m3/d)  comprised of many concrete water tanks( 5000 to 100,000  m3 ), many buildings, roads, Power Plant and Product Water Pumping Station( Designed Capacity 100,000 m3/d at 30 bar) with 2 km long 1000 mm diameter ductile iron Pipeline connected to existing 70km long 1000mm diameter ductile iron water transmission pipeline going to Bish.
Construction of 75,000 m3/d RO Water Treatment Plant ( Designed capacity extendable to 100,000 m3/d)  comprised of many concrete water tanks( 5000 to 100,000  m3 ), many buildings, roads, Power Plant and Product Water Pumping Station( Designed Capacity 100,000 m3/d at 30 bar) with 2 km long 1000 mm diameter ductile iron Pipeline connected to existing 70km long 1000mm diameter ductile iron water transmission pipeline going to Bish.
Construction of 50,000 m3/d Dam Water Pre-Treatment Plant ( Extendable to Designed Capacity 100,000 m3/d) comprised of many process concrete water structures/tanks/ ( 5000 to 50,000  m3 ). Many buildings, roads, 5500KW Power Plant, Product Water Pumping Station(100,000 m3/hr at 55 bar) and  58.5 km long 500mm diameter Carbon Steel Water Transmission line equipped with cathodic Protection, Isolation Valve/Washout Chambers and Telemetry based SCADA System going to Shuwaiba from Helli Dam.
Construction of five shallow wells(each 20,000 m3/d) complete with pump, power plant and their interconnection with ductile iron pipes up to Raw Water Tank in the plant.
Construction of 50,000 m3/d Dam Water Pre-Treatment Plant ( Extendable to Designed Capacity 100,000 m3/d) comprised of many process concrete water structures/tanks/ ( 5000 to 50,000  m3 ). Many buildings, roads, 5500KW Power Plant, Product Water Pumping Station(100,000 m3/hr at 55 bar) and  58.5 km long 500mm diameter Carbon Steel Water Transmission line equipped with cathodic Protection, Isolation Valve/Washout Chambers and Telemetry based SCADA System going to Shuwaiba from Helli Dam.
Construction of five shallow wells(each 20,000 m3/d) complete with pump, power plant and their interconnection with ductile iron pipes up to Raw Water Tank in the plant.
Construction of 50,000 m3/d Dam Water Pre-Treatment Plant ( Extendable to Designed Capacity 100,000 m3/d) comprised of many process concrete water structures/tanks/ ( 5000 to 50,000  m3 ). Many buildings, roads, 5500KW Power Plant, Product Water Pumping Station(100,000 m3/hr at 55 bar) and  58.5 km long 500mm diameter Carbon Steel Water Transmission line equipped with cathodic Protection, Isolation Valve/Washout Chambers and Telemetry based SCADA System going to Shuwaiba from Helli Dam.
Construction of five shallow wells(each 20,000 m3/d) complete with pump, power plant and their interconnection with ductile iron pipes up to Raw Water Tank in the plant.
Construction of 50,000 m3/d Dam Water Pre-Treatment Plant ( Extendable to Designed Capacity 100,000 m3/d) comprised of many process concrete water structures/tanks/ ( 5000 to 50,000  m3 ). Many buildings, roads, 5500KW Power Plant, Product Water Pumping Station(100,000 m3/hr at 55 bar) and  58.5 km long 500mm diameter Carbon Steel Water Transmission line equipped with cathodic Protection, Isolation Valve/Washout Chambers and Telemetry based SCADA System going to Shuwaiba from Helli Dam.
Construction of five shallow wells(each 20,000 m3/d) complete with pump, power plant and their interconnection with ductile iron pipes up to Raw Water Tank in the plant.
Construction of 50,000 m3/d Dam Water Pre-Treatment Plant ( Extendable to Designed Capacity 100,000 m3/d) comprised of many process concrete water structures/tanks/ ( 5000 to 50,000  m3 ). Many buildings, roads, 5500KW Power Plant, Product Water Pumping Station(100,000 m3/hr at 55 bar) and  58.5 km long 500mm diameter Carbon Steel Water Transmission line equipped with cathodic Protection, Isolation Valve/Washout Chambers and Telemetry based SCADA System going to Shuwaiba from Helli Dam.
Construction of five shallow wells(each 20,000 m3/d) complete with pump, power plant and their interconnection with ductile iron pipes up to Raw Water Tank in the plant.
Five Pumping Station Complexes, each complete with one concrete Reservoir (1,500 to 11,800 m3), Pumping Room ( 8X209 m3/hr), Power Plant, Surge Protection, Chlorination System, many Buildings, Workshop, Guard House, Boundary Wall, Tanker Filling Point and  75 km long underground ductile iron pipeline (300 to 600 mm diameter) to interconnect all five complexes for supply of water to the areas adjacent to Al Baha, Voice Communication and Remote Control Operation by SCADA System between all stations.
Five Pumping Station Complexes, each complete with one concrete Reservoir (1,500 to 11,800 m3), Pumping Room ( 8X209 m3/hr), Power Plant, Surge Protection, Chlorination System, many Buildings, Workshop, Guard House, Boundary Wall, Tanker Filling Point and  75 km long underground ductile iron pipeline (300 to 600 mm diameter) to interconnect all five complexes for supply of water to the areas adjacent to Al Baha, Voice Communication and Remote Control Operation by SCADA System between all stations.
Five Pumping Station Complexes, each complete with one concrete Reservoir (1,500 to 11,800 m3), Pumping Room ( 8X209 m3/hr), Power Plant, Surge Protection, Chlorination System, many Buildings, Workshop, Guard House, Boundary Wall, Tanker Filling Point and  75 km long underground ductile iron pipeline (300 to 600 mm diameter) to interconnect all five complexes for supply of water to the areas adjacent to Al Baha, Voice Communication and Remote Control Operation by SCADA System between all stations.
Construction of twenty shallow wells equipped pump, power plant and ductile iron pipe (200 to 600mm diameter) network supplying water to the nearby pumping station.
Construction of Five Pumping Stations, each complete with one concrete water tank (5000 to 11,800 m3), Pumping Room (8X 336 m3/hr), Power Plant, Surge Protection, Chlorination System, many Buildings, Workshop, Guard House, Fence Boundary, Communication and Remote Control(SCADA System), two Tanker Filling Stations and  120km long 600mm diameter  Ductile Iron Water Transmission PipeLine between five stations, Voice Communication and Remote Control Operation by SCADA System between all stations.
Construction of twenty shallow wells equipped pump, power plant and ductile iron pipe (200 to 600mm diameter) network supplying water to the nearby pumping station.
Construction of Five Pumping Stations, each complete with one concrete water tank (5000 to 11,800 m3), Pumping Room (8X 336 m3/hr), Power Plant, Surge Protection, Chlorination System, many Buildings, Workshop, Guard House, Fence Boundary, Communication and Remote Control(SCADA System), two Tanker Filling Stations and  120km long 600mm diameter  Ductile Iron Water Transmission PipeLine between five stations, Voice Communication and Remote Control Operation by SCADA System between all stations.
Construction of twenty shallow wells equipped pump, power plant and ductile iron pipe (200 to 600mm diameter) network supplying water to the nearby pumping station.
Construction of Five Pumping Stations, each complete with one concrete water tank (5000 to 11,800 m3), Pumping Room (8X 336 m3/hr), Power Plant, Surge Protection, Chlorination System, many Buildings, Workshop, Guard House, Fence Boundary, Communication and Remote Control(SCADA System), two Tanker Filling Stations and  120km long 600mm diameter  Ductile Iron Water Transmission PipeLine between five stations, Voice Communication and Remote Control Operation by SCADA System between all stations.
Construction of twin 165 km long 1200mm diameter CCP( Cylinder Concrete Pipe) underground Water Transmission Pipe Lines equipped with Cathodic Protection, Voice Communication & Remote Control Operation with SCADA system and  Isolation Valve Chambers /Washout Chambers from Hunai wells to HBR(High Point Reservoir) Riyadh city.
Construction of twin 165 km long 1200mm diameter CCP( Cylinder Concrete Pipe) underground Water Transmission Pipe Lines equipped with Cathodic Protection, Voice Communication & Remote Control Operation with SCADA system and  Isolation Valve Chambers /Washout Chambers from Hunai wells to HBR(High Point Reservoir) Riyadh city.
Construction of eight shallow wells, each complete with 126 m3/hr pump & related electro-mechanical accessories and their interconnecting pipeline up to 5000m3 concrete tank.Four Pumping Station Complexes, each including eight concrete Reservoir (2,000 to 22,000 m3), Pumping Room ( 2 to 5 Pumps X41 to 193 l/s), Power Plant, Surge Protection, Chlorination System, many Buildings, Workshop, Guard House, Boundary Wall, Tanker Filling Point and underground ductile iron pipeline (500 to 900 mm diameter) to interconnect all four stations for supply of water to the cities of Afif, Dawadmi and neighboring 75 villages, Voice Communication System and Remote Control Operation. ( SCADA System) between all stations.
                                
Construction of eight shallow wells, each complete with 126 m3/hr pump & related electro-mechanical accessories and their interconnecting pipeline up to 5000m3 concrete tank.Four Pumping Station Complexes, each including eight concrete Reservoir (2,000 to 22,000 m3), Pumping Room ( 2 to 5 Pumps X41 to 193 l/s), Power Plant, Surge Protection, Chlorination System, many Buildings, Workshop, Guard House, Boundary Wall, Tanker Filling Point and underground ductile iron pipeline (500 to 900 mm diameter) to interconnect all four stations for supply of water to the cities of Afif, Dawadmi and neighboring 75 villages, Voice Communication System and Remote Control Operation. ( SCADA System) between all stations.
                                
Construction of two Concrete Reservoirs, each 1,500,0000 m3 Capacity, 2.2m Diameter 5-kilometer long  PCCP. Two  Inlet Pressure Pipelines underground from Jubail SWCC Water Transmission Lines entering Riyadh City to High Point Reservoirs & 2.2m Diameter 5 kilometer long  PCCP Two outlet Gravity Pipelines underground from Reservoirs to Riyadh City Water Supply Network complete with motorized isolation valve Chambers/Washout Chambers, Gas Chlorination System equipped with Power Plant & Control System, Telemetry based SCADA System for pipelines.  Supply Network complete with motorized isolation valve Chambers/Washout Chambers, Gas Chlorination System equipped with Power Plant & Control System, Telemetry based SCADA System for pipelines. .
Construction of two Concrete Reservoirs, each 1,500,0000 m3 Capacity, 2.2m Diameter 5-kilometer long  PCCP. Two  Inlet Pressure Pipelines underground from Jubail SWCC Water Transmission Lines entering Riyadh City to High Point Reservoirs & 2.2m Diameter 5 kilometer long  PCCP Two outlet Gravity Pipelines underground from Reservoirs to Riyadh City Water Supply Network complete with motorized isolation valve Chambers/Washout Chambers, Gas Chlorination System equipped with Power Plant & Control System, Telemetry based SCADA System for pipelines.  Supply Network complete with motorized isolation valve Chambers/Washout Chambers, Gas Chlorination System equipped with Power Plant & Control System, Telemetry based SCADA System for pipelines. .
Construction of two Concrete Reservoirs, each 1,500,0000 m3 Capacity, 2.2m Diameter 5-kilometer long  PCCP. Two  Inlet Pressure Pipelines underground from Jubail SWCC Water Transmission Lines entering Riyadh City to High Point Reservoirs & 2.2m Diameter 5 kilometer long  PCCP Two outlet Gravity Pipelines underground from Reservoirs to Riyadh City Water Supply Network complete with motorized isolation valve Chambers/Washout Chambers, Gas Chlorination System equipped with Power Plant & Control System, Telemetry based SCADA System for pipelines.  Supply Network complete with motorized isolation valve Chambers/Washout Chambers, Gas Chlorination System equipped with Power Plant & Control System, Telemetry based SCADA System for pipelines. .
Construction of two Concrete Reservoirs, each 1,500,0000 m3 Capacity, 2.2m Diameter 5-kilometer long  PCCP. Two  Inlet Pressure Pipelines underground from Jubail SWCC Water Transmission Lines entering Riyadh City to High Point Reservoirs & 2.2m Diameter 5 kilometer long  PCCP Two outlet Gravity Pipelines underground from Reservoirs to Riyadh City Water Supply Network complete with motorized isolation valve Chambers/Washout Chambers, Gas Chlorination System equipped with Power Plant & Control System, Telemetry based SCADA System for pipelines.  Supply Network complete with motorized isolation valve Chambers/Washout Chambers, Gas Chlorination System equipped with Power Plant & Control System, Telemetry based SCADA System for pipelines. .
Construction of Eight shallow wells, each complete with 30 l/s pump powered by overhead Electric Transmission line & related electro-mechanical accessories and their interconnecting pipe line up to first 11,800 m3 concrete tank.
Construction of Eight shallow wells, each complete with 30 l/s pump powered by overhead Electric Transmission line & related electro-mechanical accessories and their interconnecting pipe line up to first 11,800 m3 concrete tank.
Construction of Eight shallow wells, each complete with 30 l/s pump powered by overhead Electric Transmission line & related electro-mechanical accessories and their interconnecting pipe line up to first 11,800 m3 concrete tank.
Construction of Pumping Station and ductile iron pipe (300 mm to 900 mm) network for the supply of drinking water to Hafr Al Batin and Qaisumah area including valve and Flowmeter chambers.
Construction of Pumping Station and ductile iron pipe (300 mm to 900 mm) network for the supply of drinking water to Hafr Al Batin and Qaisumah area including valve and Flowmeter chambers.
Construction of Pumping Station and ductile iron pipe (300 mm to 900 mm) network for the supply of drinking water to Hafr Al Batin and Qaisumah area including valve and Flowmeter chambers.
Construction of Eight shallow wells, each complete with 30 l/s pump powered by overhead Electric Transmission line & related electro-mechanical accessories and their interconnecting pipe line up to first 11,800 m3 concrete tank.
Construction of Pumping Station and ductile iron pipe (300 mm to 900 mm) network for the supply of drinking water to Hafr Al Batin and Qaisumah area including valve and Flowmeter chambers.